XTX Markets Opens Finnish Data Center, Says Red Tape Puts Expansion at Risk

Tuesday, 24/11/2026 | 10:30 GMT by Damian Chmiel
  • The 22.5-megawatt site in Kajaani is live, but grid power is secured only for the first two buildings.
  • Permits to take land for power lines now take years, the trading firm's operating chief said.
Source: XTX Markets
Source: XTX Markets

XTX Markets has opened its first own data center, a 22.5-megawatt facility in Kajaani, Finland, the London-based trading firm said today (Tuesday). It warned that slow permits for new power lines could put further investment there at risk.

Power is secured for two buildings. XTX said electricity and grid connections cover only the first two facilities on the 193-hectare campus, while a third, already under construction and due in mid-2028, has no guaranteed supply yet.

That leaves the site well short of the 250 megawatts XTX aimed for when the Kajaani plan surfaced in April 2024. The capacity now running equals 9% of that target, by FinanceMagnates.com's calculation.

London's trading industry is coming home!

XTX said it has spent more than €400 million (about $465 million) on construction so far, mostly with Finnish contractors. That is roughly 40% of the more than €1 billion it earmarked for the site in January 2025.

Power Line Permits Now Take Years

The delay XTX describes concerns the lines that would carry electricity to the later buildings. Mike Irwin, chief operating officer at XTX Markets, singled out permits to expropriate land for those lines.

Mike Irwin, Chief Operating Officer at XTX Markets
Mike Irwin, Chief Operating Officer at XTX Markets

"Expropriation permits that once took months can now take years," Irwin said.

He said government bureaucracy and a lack of engagement were putting plans to invest billions more at risk. XTX would contribute financially to infrastructure, he added, but without that engagement future investment decisions would be called into question.

Finnish public broadcaster Yle reported that XTX plans five data centers along the Kajaani River and would build faster with enough power. Three of the five therefore depend on electricity that is not yet secured.

From a Leased Site to Its Own Campus

Kajaani was built to end XTX's reliance on rented computing. When the €1 billion figure came out, then-Chief Technology Officer Joshua Leahy said the firm's need for compute had outgrown leasing options. Leahy left XTX and its board in March 2026.

The move off leased space is now done for storage. In one six-week window, XTX said, it shifted 417 petabytes on 385 servers, roughly 17,000 drives weighing 26 metric tons, from a rented data center five kilometers away. The second building is due to start operating in 2027.

A Profitable Firm Asking for Grid Access

Money is not the constraint XTX names. Its three UK entities reported combined net revenue of £3.93 billion (about $5.3 billion) for 2025, up 43% from a year earlier, and profit after tax of £1.71 billion.

The firm, controlled by founder Alex Gerko, ran more than 25,000 graphics processing units for research in 2024, mostly from Nvidia. Its models price more than 53,000 instruments.

The Kajaani site employs more than 30 full-time staff and has room for 50. XTX also pledged more than €1.6 million to Finnish education projects, including €520,000 for Kajaani University of Applied Sciences.

XTX Markets has opened its first own data center, a 22.5-megawatt facility in Kajaani, Finland, the London-based trading firm said today (Tuesday). It warned that slow permits for new power lines could put further investment there at risk.

Power is secured for two buildings. XTX said electricity and grid connections cover only the first two facilities on the 193-hectare campus, while a third, already under construction and due in mid-2028, has no guaranteed supply yet.

That leaves the site well short of the 250 megawatts XTX aimed for when the Kajaani plan surfaced in April 2024. The capacity now running equals 9% of that target, by FinanceMagnates.com's calculation.

London's trading industry is coming home!

XTX said it has spent more than €400 million (about $465 million) on construction so far, mostly with Finnish contractors. That is roughly 40% of the more than €1 billion it earmarked for the site in January 2025.

Power Line Permits Now Take Years

The delay XTX describes concerns the lines that would carry electricity to the later buildings. Mike Irwin, chief operating officer at XTX Markets, singled out permits to expropriate land for those lines.

Mike Irwin, Chief Operating Officer at XTX Markets
Mike Irwin, Chief Operating Officer at XTX Markets

"Expropriation permits that once took months can now take years," Irwin said.

He said government bureaucracy and a lack of engagement were putting plans to invest billions more at risk. XTX would contribute financially to infrastructure, he added, but without that engagement future investment decisions would be called into question.

Finnish public broadcaster Yle reported that XTX plans five data centers along the Kajaani River and would build faster with enough power. Three of the five therefore depend on electricity that is not yet secured.

From a Leased Site to Its Own Campus

Kajaani was built to end XTX's reliance on rented computing. When the €1 billion figure came out, then-Chief Technology Officer Joshua Leahy said the firm's need for compute had outgrown leasing options. Leahy left XTX and its board in March 2026.

The move off leased space is now done for storage. In one six-week window, XTX said, it shifted 417 petabytes on 385 servers, roughly 17,000 drives weighing 26 metric tons, from a rented data center five kilometers away. The second building is due to start operating in 2027.

A Profitable Firm Asking for Grid Access

Money is not the constraint XTX names. Its three UK entities reported combined net revenue of £3.93 billion (about $5.3 billion) for 2025, up 43% from a year earlier, and profit after tax of £1.71 billion.

The firm, controlled by founder Alex Gerko, ran more than 25,000 graphics processing units for research in 2024, mostly from Nvidia. Its models price more than 53,000 instruments.

The Kajaani site employs more than 30 full-time staff and has room for 50. XTX also pledged more than €1.6 million to Finnish education projects, including €520,000 for Kajaani University of Applied Sciences.

About the Author: Damian Chmiel
Damian Chmiel
  • 4226 Articles
  • 120 Followers
About the Author: Damian Chmiel
Damian Chmiel is a Senior Analyst & Editor at Finance Magnates with more than 15 years of experience in the CFD and online trading industry. Active as both a trader and journalist since 2010, he focuses on broker coverage, fintech innovation, and regulatory developments across Europe, the Middle East, and Asia. His work includes interviews with C-level leaders at major brokerages and fintech platforms, as well as co-authoring Finance Magnates’ quarterly industry benchmarking reports. Damian’s reporting is data-driven, market-aware, and grounded in direct industry engagement. His analysis and commentary have also been cited by external media outlets, including Investing.com, Binance, The Asset, Stockhead, and Dispatch. Education: MA in Finance and Accounting, Cracow University of Economics
  • 4226 Articles
  • 120 Followers

More from the Author

Institutional FX

!"#$%&'()*+,-./0123456789:;<=>?@ABCDEFGHIJKLMNOPQRSTUVWXYZ[\]^_`abcdefghijklmnopqrstuvwxyz{|} !"#$%&'()*+,-./0123456789:;<=>?@ABCDEFGHIJKLMNOPQRSTUVWXYZ[\]^_`abcdefghijklmnopqrstuvwxyz{|}